Nine stages from the first meeting to the end of the warranty period

The HOAI divides the architect's work into nine work stages (Leistungsphasen). Each stage carries a fixed share of the fee (§ 34(3) HOAI) and includes specific basic services listed in Annex 10.1. Knowing the stages helps you understand what you are paying for and lets you commission individual stages. In the HOAI fee calculator you can switch each stage on or off.

Stage 1: Basic evaluation (2%)

The architect clarifies the brief with you: room schedule, budget, timeline, site and legal framework. They advise on further needs, for example whether structural or building services engineers are required. The result is a shared basis for the design.

Stage 2: Preliminary design (7%)

The first sketches and options are produced. The architect develops a design concept, checks it against building law, holds initial talks with authorities and prepares the cost estimate under DIN 276. This estimate serves as a provisional basis for your financing.

Stage 3: Final design (15%)

The chosen concept becomes a fully worked-out design, usually at a scale of 1:100. Structure, building services and materials are integrated. The stage ends with the cost calculation, which is normally the final basis for the fee. The final design is the point at which the form of the building is fixed.

Stage 4: Planning permission (3%)

The architect prepares the planning documents and submits the building application. They follow the procedure until permission is granted and supply additional documents if the authority asks. For interiors this stage is worth 2%, because permission is often not required.

Stage 5: Construction documents (25%)

The construction documents translate the design into working and detail drawings at scales from 1:50 to 1:1, from which the trades build. At 25% for buildings and 30% for interiors, it is the second-largest stage. Mistakes here become expensive on site, so careful commissioning pays off.

Stage 6: Preparing the tender (10%)

The architect determines quantities and prepares the bills of quantities used to obtain bids from contractors. A schedule is drawn up and the cost calculation is compared with the priced bills of quantities.

Stage 7: Assisting with the award (4%)

Bids are obtained, checked, compared and negotiated. The architect prepares a price comparison, recommends awards and assists in placing the contracts. They compare the costs with the results of the award so that you spot deviations early.

Stage 8: Site supervision (32%)

The largest stage: the architect checks that construction matches the permit, drawings and contracts, coordinates the trades, keeps the site diary, checks invoices, tracks costs and deadlines and organises acceptance. Because of the time spent on site it is worth 32%.

Stage 9: Post-completion support (2%)

After handover, the architect assesses defects found within the limitation periods, for at most five years from acceptance. Before the periods expire, they inspect the building to identify defects and assist in releasing retention securities. Supervising the remedy of defects, on the other hand, is a special service and must be agreed separately.

Partial commissioning: what is allowed?

You do not have to commission all stages at once. Under § 8(1) HOAI, only the percentages of the commissioned stages may then be charged. Commissioning in steps is common: stages 1 to 4 first (27% for buildings), then stages 5 to 9 after planning permission. If only some basic services within a stage are commissioned, only the corresponding share is payable (§ 8(2)).

At €400,000 eligible costs in zone III at the middle rate, stages 1 to 4 together come to about €15,606 net and stages 5 to 9 to about €42,193. The HOAI fee calculator shows the exact value for your project in the bar chart per work stage.

Conclusion

The work stages make the architect's fee transparent. Almost 60% of the fee goes on construction documents and site supervision; cutting here is often a false economy. The main article Calculating architect fees in Germany explains how the stages feed into the overall calculation.